OFFICE OF STATE AID ROAD CONSTRUCTION
MISSISSIPPI DEPARTMENT OF TRANSPORTATION
AND
FORREST COUNTY BOARD OF SUPERVISORS
SECTION 900
NOTICE TO CONTRACTORS:
Sealed bids will be received by the Board of Supervisors of Forrest County,
Mississippi at the Forrest County Courthouse, Hattiesburg, Mississippi, until 10:00
am on the 4th day of June, 2018 and shortly thereafter publicly opened for the
construction of 22.989 miles of OVERLAY on ROAD 'A' - 'I' being known as Project No.
SAP-18(15)M in Forrest County, Mississippi.
PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:
ITEM QUANTITY UNIT
ROADWAY ITEMS:
MOBILIZATION LUMP SUM LS
REMOVAL OF ASPHALT PAVEMENT, 5,042.000 SY
ALL DEPTHS
REMOVAL OF PIPE (ALL SIZES) 133.000 LF
UNCLASSIFIED EXCAVATION (FM) 1,269.000 CY
BORROW EXCAVATION (CONTRACTOR 48.000 CY
FURNISHED) (LVM) CLASS 6
STRUCTURE EXCAVATION 89.000 CY
GRANULAR MATERIAL (LVM) 4,536.000 CY
(CLASS 6, GROUP "E")
HOT MIX ASPHALT, ST, 9.5 mm 8,144.000 TON
HOT MIX ASPHALT, ST, 19 mm 2,512.000 TON
(BASE REPAIR)
HOT MIX ASPHALT, ST, 9.5 mm, 2,806.000 TON
LEVELING
ULTRA-THIN ASPHALT PAVEMENT, UHMA 8,540.300 TON
18" REINFORCED CONCRETE PIPE, 32.000 LF
CLASS III
24" REINFORCED CONCRETE PIPE, 32.000 LF
CLASS III
42" REINFORCED CONCRETE PIPE, 32.000 LF
CLASS III
18" REINFORCED CONCRETE PIPE, 2.000 EA
END SECTION
24" REINFORCED CONCRETE PIPE, 2.000 EA
END SECTION
42" REINFORCED CONCRETE PIPE, 2.000 EA
END SECTION
MAINTENANCE OF TRAFFIC LUMP SUM LS
ADDITIONAL CONSTRUCTION SIGNS 0.000 SF
4" WIDE THERMOPLASTIC EDGE STRIPE 45.956 MI
(CONTINUOUS WHITE) (60 MILS)
4" WIDE THERMOPLASTIC TRAFFIC 13.016 MI
Page 1 of 3
SECTION 900
PROJECT NO. SAP-18(15)M
FORREST COUNTY
STRIPE (SKIP YELLOW) (90 MILS)
4" WIDE THERMOPLASTIC TRAFFIC 148,025.000 LF
STRIPE (CONTINUOUS YELLOW)
(90 MILS)
THERMOPLASTIC LEGEND 5,160.000 LF
(WHITE) (120 MILS)
THERMOPLASTIC LEGEND 125.000 SF
(WHITE) (120 MILS)
TWO-WAY CLEAR REFLECTIVE RAISED 1,430.000 EA
MARKERS
TWO-WAY YELLOW REFLECTIVE RAISED 3,039.000 EA
MARKERS
REFLECTORIZED TRAFFIC WARNING SIGN 115.000 EA
(ENCAPSULATED LENS)
REFLECTORIZED TRAFFIC REGULATORY 64.000 EA
SIGN (ENCAPSULATED LENS)
REFLECTORIZED TRAFFIC OBJECT MARKER 56.000 EA
(ENCAPSULATED LENS)(TYPE 3)
EROSION CONTROL ITEMS:
AGRICULTURAL LIMESTONE 13.200 TON
COMMERCIAL FERTILIZER (13-13-13) 6.600 TON
AMMONIUM NITRATE 1.300 TON
SEEDING 6.600 AC
VEGETATIVE MATERIALS FOR MULCH 13.200 TON
Page 2 of 3
PROJECT NO. SAP-18(15)M
FORREST COUNTY
NOTICE TO CONTRACTORS:
CONTRACT TIME: 60 Working Days
BASIS OF AWARD
The award, if made, will be made to the lowest qualified bidder on the basis of
published quantities.
The Board of Supervisors hereby notifies all bidders that it will affirmatively
insure that in any contract entered into pursuant to this advertisement, minority
business enterprise will be afforded full opportunity to submit bids in response to
this invitation and will not be discriminated against on the grounds of race, color,
or national origin in consideration for an award.
PLANS AND SPECIFICATIONS are on file in the Office of the Chancery Clerk of Forrest
County, the County Engineer's office and the Office of the State Aid Engineer, 412
E. Woodrow Wilson Avenue, Jackson, Mississippi. This project shall be constructed
in acccordance with the latest edition of the Mississippi Standard Specifications
for State Aid Road and Bridge Construction.
PLANS AND PROPOSALS may be downloaded from Central Bidding at www.centralbidding.com.
Electronic bids can be submitted at www.centralbidding.com. For any questions
relating to the electronic bidding process, please call Central Bidding at
225-810-4814.
Certified check or bid bond for five percent (5%) of the total bid, made payable to
Forrest County and the State of Mississippi must accompany each proposal.
Bidders are hereby notified that any proposal accompanied by letters qualifying in
any manner the condition under which the proposal is tendered will be considered an
irregular bid and such proposal will not be considered in making the award.
David Hogan, President
Forrest County Board of Supervisors
Advertise: May 3, 2018