ADVERTISEMENT FOR BIDS
BID NO. 50-00123477
 
 
Sealed Bids will be received in the West Bank Purchasing Department, Suite 4400, Jefferson Parish General Government Building, 200 Derbigny Street, Gretna, LA 70053 until 2:00pm, November 8, 2018 and publicly opened thereafter. At no charge, bidders may submit via Jefferson Parish’s electronic procurement page by visiting www.jeffparishbids.net to register for this free site. For convenience, bidders may also submit bids in the East Bank Purchasing Department, Suite 404, Jefferson Parish Joseph S. Yenni Building, 1221 Elmwood Park Blvd., Jefferson, LA 70123. However, if submitting bids on the day of bid opening, bidders must submit at the West Bank location only. All bids will be publicly opened at the West Bank location at 2:00pm for the following project:
 

US-61 From David Drive to Transcontinental Drive Roadway Lighting Improvements Public works project number 2012-041-SL

 
All bids must be in accordance with the contract documents on file with the Jefferson Parish Purchasing Department, Suite 4400, Jefferson Parish General Government Building, at 200 Derbigny Street, Gretna, Louisiana. All bidders must show the Bid Number on the outside of their bid envelope.  Late bids will not be accepted.
 
Each Bid must be accompanied by certified check, cashiers check, or bid bond acceptable to the owner in the amount equal to five percent (5%) of the total amount bid, and payable without condition to the owner. If submitting a bid online, vendors must submit an electronic bid bond through the respective online clearinghouse bond management system(s) as indicated in the electronic bid Solicitation on Central Auction House.  No scanned paper copies of any bid bond   will be accepted as part of the electronic bid submission.
 
The drawings and specifications are on file and open for inspection in the Jefferson Parish Purchasing Department, Suite 4400, Jefferson Parish General Government Building, at 200 Derbigny Street, Gretna, Louisiana. A complete set of Contract Documents may be secured from Gulf Engineers & Consultants, INC., 8282 Goodwood Boulevard, Baton Rouge, LA 70806  (PHONE 225-612-3000, FAX 225-612-3022) by licensed contractors upon receipt of $90.00 per set. Deposit on the first set of documents furnished bona fide prime bidders will be fully refunded upon return of documents in good condition no later than ten (10) days after receipts of bids.
 
The successful bidder will be required to furnish a performance bond guaranteeing faithful performance of the contract. Companies providing the bonds shall comply with the requirements   of LRS-R.S. 38:2218 and R.S. 38:2219 as applicable.
 
The Jefferson Parish Council reserves the right to reject all bids and to reject bids for just cause, pursuant to the law. Jefferson Parish and its partners as the recipients of federal funds are fully committed to awarding a contract(s) to firm(s) that will provide high quality services and that are dedicated to diversity and to containing costs. Thus, Jefferson Parish strongly encourages the involvement of minority and/or woman-owned business enterprises (DBE’s, including MBE’s, WBE’s and SBE’s) to stimulate participation in procurement and assistance programs.
 
All prospective bidders are invited to attend this non-mandatory pre-bid conference which will be held at 10:00 am on October 25, 2018 in the Jefferson Parish Purchasing Department, located at 200 Derbigny St., Suite 4400, Gretna, LA  70053. However, failure to attend the pre-bid conference shall not relieve the bidder of responsibility for information discussed at the conference.
 
 
ADV-1
Furthermore, failure to attend the pre-bid conference and inspection does not relieve the successful bidder from the necessity of furnishing materials or performing any work that may be required to complete the work in accordance with the specification with no additional cost to the owner.
 
 
Renny Simno                                                                                      Jenifer Lotz
Director                                                                                               Chief Buyer
Purchasing Department                                                                      Purchasing Department
 

ADV: The Times Picayune: October 10, 17, and 24, 2018

 
For additional information, please visit the Purchasing Webpage at
http://purchasing.jeffparish.net or you may call at 504-364-2678.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ADV-2
 

SUBMITTAL INFORMATION
Creator Username: MOVALLE
Submittal Privacy: Response Encryption
Started: 10-Oct-2018 8:30:00 AM CDT
Ends: 04-Dec-2018 2:00:00 PM CST ( Expired )
History: 1190 Views, 11 Messages
Event Status: Archived event
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
PUBLIC MESSAGE BOARD
Discuss questions with the owner/creator of this Listing.
AllGreen on 10-Oct-2018 6:03:01 PM CDT
The specifications of the luminaires read they are to be 245 watts, but the drawings read they are 190 watts - which is it ?
AllGreen on 12-Oct-2018 2:17:52 PM CDT
The specifications of the luminaires read they are to be 245 watts, but the drawings read they are 190 watts - which is it ?
MOVALLE on 16-Oct-2018 9:28:58 AM CDT
A response to your question will be provided through addendum # 1 which will be processed after the pre-bid conference. If you have any further questions please feel free to email them to [email protected]. Thank you
DECO on 05-Nov-2018 3:14:55 PM CST
When will the Addenda be released for this project? Will the project bid date be pushed to a later date?
MOVALLE on 05-Nov-2018 4:12:13 PM CST
We are still working on the addendum and yes, it will postpone the bid opening date. The new date will be included on the addendum.
CivilDivision on 08-Nov-2018 1:41:08 PM CST
Per the detail included in addendum 1 now shows a double arm pole with banner arm provisions however the pole and arm wording on page 2 of 12 Note 2 says "28ft with a 6ft arm with a 2 ft rise", which do we use?
MOVALLE on 08-Nov-2018 1:49:39 PM CST
I have received your question and will forward to the appropriate contacts for a response and address through Addendum # 2 if needed. Thank you,
hitechelectricnola on 08-Nov-2018 1:58:00 PM CST
In spec section 730 Electrical Systems, Item No. 730-08-00200 Electrical Service Point references lighting panels "HLA and HLB" on sheet E304. What sheet number are these panel schedules and riser diagram shown on, and where are they located on the site plans?
MOVALLE on 08-Nov-2018 2:00:59 PM CST
I have received your question and will forward to the appropriate contacts for a response and address through Addendum # 2 if needed. Thank you,
Galcan on 15-Nov-2018 9:18:23 AM CST
Where will we be receiving the power from? Also, the drawings does not show where the panels should go. Will this be in addendum #2 as well?
MOVALLE on 19-Nov-2018 4:29:32 PM CST
I have received your question and will forward to the appropriate contacts for a response and address through Addendum # 2 if needed. Thank you,
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
29-Nov-2018 12:51:21 PM CST
UPLOADED ADDEDNUM NO. 2 WHICH CANCELS BID
08-Nov-2018 12:16:55 PM CST
UPLOADED ADDENDUM # 1 AND POSTPONED BID OPENING DATE