Replace Multiple Boilers at Various Campuses - MGCCC Attachment: Boiler Replacement Construction Specifications.pdf 
Mississippi Gulf Coast Community College - MS
Solicitation: 86561758
Listing Information/Advertisement
Project involves replacing 4 boilers: one boiler at Bldg K at Jefferson Davis Campus, Gulfport, MS, one Boiler at Bldg F, Jackson County Campus, Gautier, and two boilers at Perkinston Campus, Perkinston,MS with one boiler for Owen Hall and one boiler for Moran Hall.  The projects shall include demolition of existing boilers with replacement that will include new pumps, flues, gas line connections, hot water supply and return runouts/mains, valves, recharging of chemical of loop, and integration of Bacnet ready boilers into the Siemens front end.  New pumps shall include all accessories per drawings and specifications and connection into Siemens front end.  Insulate all piping and fittings per specifications.  Disconnect and reconnect all electrical from old and reconnect to new boiler with new disconnect and conductors.  New pumps shall be addressed similar to boilers using new vfd for disconnect and connection to Siemens front end.  VFD shall be for balancing purposes.  At Moran Hall all of the exterior roof mounted hot water piping shall be reinsulated its in entirety and shall include aluminum jacket with new roof supports.   

BID SUBMITTAL INFORMATION
Creator Username: StephensMechanical
Bidding Privacy: Bid encryption
Started: 06-Dec-2018 06:00:00 PM
Ends: 17-Jan-2019 02:00:00 PM ( 9h, 45m+ )
History: 159 Views
Event Status: Event open for bids
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
15-Jan-2019 06:47:57 PM
for information only - plan holders known to this office
15-Jan-2019 03:10:45 PM
adds dates for addenda #1 and #2 for bid form, revises Jackson County plan with fully condensing boiler and revised flue routing
09-Jan-2019 12:10:39 PM
Addendum #2 had erroneous time for the Perkinston Campus walk through listed as 9:00 am - the correct time will be 1:00 pm Jan 10, 2019, Jefferson Davis will be 9:30 am Jan 10.
08-Jan-2019 05:12:15 PM
any references to "furnished by owner" in specs and drawings should be omitted - contractor shall furnished all materials and labor, adds condensing boiler specification, establishes job site visits with schedules and locations.
08-Jan-2019 05:11:34 PM
any references to "furnished by owner" in specs and drawings should be omitted - contractor shall furnished all materials and labor, adds condensing boiler specification, establishes job site visits with schedules and locations.
21-Dec-2018 01:05:10 PM
addendum #1 posted - changes bid date to January 17, 2019 @ 2:00, references Central Bidding as electronic bid alternative.
21-Dec-2018 12:15:04 PM
disabled public message board